Compressor Station on Mari Gas Pipeline

120 MMscfd Gas Boosting Station Design, Supply, Installation, Testing, and Commissioning of complete facility of Gas Pressure Boosting Compressor station on Mari Gas Pipeline near central manifold Well No. 6 at Daharki

 

Client: CPGCL
Duration: 06 Months
Value: USD 4 millions
Executed year: 2017
Scope of work:

 

·         Design, Supply, Installation, Testing and Commissioning of complete facility of Gas Pressure Boosting Compressor  station on Mari Gas Pipeline near central manifold Well No. 6 at Daharki

·         Engineering

·         Equipment & Material Supplies

·         Construction

·         Commissioning

 

Procured Equipments ·         2 x 525 KW Jenbacher J320 Power Generation Facility

·         Transformers

·         Air Compressors

·         Switchgears / LV Panels

·         FW UL Listed Pumps

·         Pipes, Fittings & Valves

·         Cables

·         Instrumentation