30 MMscfd Gas Processing Facility
Establishment of Tolanj Processing Facility on EPC Basis by Relocating Makori EPF and Construction of Tolanj X-1 Welhead Surface Facility
Client: | MOL Pakistan |
Duration: | 12 Months |
Value: | 2M USD |
Executed year: | 2016 |
Scope of work:
|
1)Engineering Validation 2)Equipment & Material 3)Supplies 4)Construction 5)Commissioning |
Procured Equipments | 1) Pipes, Fittings & Valves 2) Electrical Cables 3) FW Network 4) Juntion Boxes 5) Cable Glands 6) Cable Trays |